Analysis of active power load dispatch in economic and environmental aspects with pseudo power flow
Abstract
In this paper a methodology with Pseudo power load flow implementation has been presented to remove extra burden on slack bus in both economic and environmental aspects. Using this methodology, the effect of nature of power plant (Thermal/Gas) has been analyzed on the generation cost, emission and power loss distribution. This work can be applied to any system as it is not dependent on type as well as the nature of system. The complete methodology has been tested on IEEE-30 bus test system with supporting numerical and graphical results.