Optimizing Commissioning Scheduling EPCC Industry Projects by Integrating AHP and CPM Methods

  • Anissa Ghaisani Syaputri, Muhammad Dachyar, Djoko Sihono Gabriel

Abstract

Engineering Procurement Construction Commissioning (EPCC) project has a trial/testing
phase to achieve the performance guarantee required in the contract before the plant handed
over to the operator. This project has enormous challenges, such as overlapping phases and
interdependencies between activities, very accurate details of activities, and uncertainties in the
accuracy of predictions that arise during the project. Many EPCC project scheduling is not
aligned with commissioning schedule. Therefore, time and resource arrangements are an
important factor in the successful completion of plant commissioning. This paper aims to
minimize commissioning delays by increasing commissioning scheduling in gas processing
industry plant projects using the Analytical Hierarchy Process (AHP) and Critical Path Method
(CPM). AHP method produces a commissioning system priorities, then used in CPM scheduling.
The results showed a short duration commissioning schedule, because of some parallel activities
between pre-commissioning and construction. The duration of completion commissioning time
reduces from 309 days to 293 days.

Published
2020-05-01
How to Cite
Anissa Ghaisani Syaputri, Muhammad Dachyar, Djoko Sihono Gabriel. (2020). Optimizing Commissioning Scheduling EPCC Industry Projects by Integrating AHP and CPM Methods. International Journal of Advanced Science and Technology, 29(7s), 3580-3587. Retrieved from http://sersc.org/journals/index.php/IJAST/article/view/17657